Balcony Retiled-U15

Due to a large area of balcony tiles tenting a few weeks ago, and an inspection by a Tiler to assess the best option for repair, we opted to do a complete retile. Our unit is on the North of Waves and gets significant sun in the winter. Tiles expand more than the concrete slab beneath and they become un-stuck. The unit directly below us had the same issue a few years ago and had to do a complete retile of their balcony.

We found a nice grey replacement tile at Tile Merchants, in Virginia. Size is 450mm square. The colour is slightly darker than the original tiles, and very close to the shale-grey used around the Waves building.

Step one was to have the air conditioner disconnected and stored away from the balcony. This proved more costly than anticipated, but was necessary.

Then we had to clear the balcony of all our furniture and plants and storage boxes. Luckily we had room in our parking bay for some of this temporary relocation of “stuff”.

The start day arrived and we had a skip bin delivered to get rid of the old tiles and dust. This was an extra expense we were advised of as we had to organise the bin.

Having previously had bathroom renovations, we were mindful of protecting our flooring. We found a roll of temporary floor protection at Bunnings. We had a path from the lift to the balcony doors.

Jack hammering started about 8:00am on Monday. By about 11am all the tiles had been lifted. The crew left that afternoon and cleaned up the tiles the next morning and dumped them in the skip bin.

Next stage was to sweep the area ready for grinding. They only ground back to the glue/screed layers ready for levelling and application of waterproofing. Two applications of waterproofing were applied over two days using “Hydra Ban Slurry”.

The waterproofing was done with 2 coats of Hydra Ban Slurry. It looked very effective once it had soaked in and dried.

Here we show the waterproofed area during drying, ready for some levelling fill and then the new glue and tiles.

Three rows along the balcony edge are done on Day-4. Looking great.

A closer photo of a completed area, ready for grout on Day-5.

As I post this article we are at the end of Day-4. Tomorrow will be the grouting of the tiles, which should be done by lunchtime. Then on Day-6 they plan to return to finish off with some sealant around all the edges. All in all it took less time than expected and the workmanship is great.

Should you want a quote for your balcony then the contractor we used was “Starsh”, and his phone number is 0431 165 919. He was recommended to us by “Tile Merchants” where we bought our tiles.

Cyclone Alfred Thursday Update

The Cyclone Threat Continues

We are still in the path of the Alfred Cyclone. The actual forecast path keeps changing, but currently it is at Deception Bay. Not good for Redcliffe as we will cop the strong winds on the south side of the eye.

 

Thursday Afternoon Track Forecast

Path forecast of 4/3/2025

Alfred Still Aims For Us

Expected Path

 Tuesday Afternoon Update ... Now showed as aiming for deception Bay.

 

We remain in the expected path of the effects of Cyclone Alfred. Today's forecast shows it coming ashore at the north end of Bribie Island.

Being on the south side we expect some strong winds Thursday night/Friday morning.

As At Tues Afternoon

Path forecast of Tues Afternoon

Path forecast of 4/3/2025

Path forecast of 4/3/2025

Alfred Update Mon 3rd March

Get Your Supplies Yesterday

 An update as at 2:00pm Monday 

The local Woolworths at Bluewater Square, and I suspect Margate, are completely OUT OF bottled water. And I suspect Toilet paper.

Also, the queues to check-out are Longgggg.

For water backup, we bought some new plastic buckets from "crap-tastic" just across the lobby from Woolworths.

 

Latest Track

Updated forecast tracking issued Monday 3rd March 2025...

Latest cyclone track shows the landfall is expected further north of us than shown yesterday. This does not help us much as the strongest winds will be south of the eye.

Landfall now shows as happening about 4:00am Friday. See the track shown below.

As we get further into the week we will monitor the changes and report back here.

See also the official details published by Bureau of Meteorology...

http://bom.gov.au/

and TV/Radio/phone alerts.

Latest Track

Cyclone Alfred Alert

Prepare Balconies

There is a chance that the  Cyclone Alfred  will be a direct hit on  Redcliffe  around Thursday 6th March-Friday 7th March 2025.

Here are some path predictions as at Sunday 2nd March:-

The images show the forecast path.  The dashed line shows the closeup location where the cyclone is aiming at the Redcliffe Peninsular.

Be Prepared

A near miss with a cyclone (Oswald) happened on Australia Day weekend 2013. Winds were very strong at Waves and most items on balconies were blown away. This included chairs and tables.  a glass balcony panel was shattered.  All from remnants of a cyclone that went ashore north of Bribie Island.

This time we are in the firing line.

 Some Recommended Actions

Either bring all balcony furniture inside  or  Gather furniture items together and tie them to a balcony column with strong rope.

Remove any items hanging on balconies.

Plants should be brought inside, or taken to your parking bay

Ensure your sliding doors and windows are fully closed and latched. This is important as when fully closed, the doors and frames interlock for added strength. Do not leave doors open even a few millimetres. Our doors and windows are built with glass rated for strong winds.

 

 

25 Marine Pde

25 Marine Parade

Planned Building Next Door to Waves

Newsflash --  5-Nov-2024

Some disturbing news for Waves.

The vacant lot next door at 25 Marine Parade looks likely to become a high rise apartment building.

Click the link below to see the basic plans for the site.

PDF of Plans

25 Marine Pde

Nearby Development

The Location

The old yellow house on the corner of Marine Pde and Ella St looks set to be replaced soon with an 8 storey 24 Unit apartment building.

 

The property shows it was recently sold for the second time this year. It had Development Approval (DA3833) for the new building.

On 27th September 2023 there was a large drilling truck there with a team drilling deep test holes.

The design shows 8 levels, with 3 Lots on each level, and 2 levels of below ground parking. Most  lots have two stacked parking bays and bicycle storage.

There is no indication of when the development might begin.

Fibre Internet at Waves

Updated with New Pricing from December 2022

This article updated as TPG and iiNet have increased prices for new customers. It is still a great deal for a great service.

Waves now has about 18 units connected and all are happy with the service.

Latest Technology News – Internet

TPG Communications has connected a glass fibre network connection to our building.

This opens up opportunities for those wanting faster unlimited internet services to help resolve some video streaming issues.

You can sign up via TPG or via  iiNet. iiNet is a TPG subsidiary company. Internode is another option.

You also have an opportunity to save on existing NBN internet costs, depending on your service speeds and capacity packages.

Today, 22-June-2021, four units were connected to the recently available TPG FTTB (Fibre To The Basement) at Waves.

============================================================================

Things to Consider Before Switching

  • You may be locked into a contract with your existing internet provider
  • You may be using an email address bundled with your existing NBN provider.
  • You may have an existing Mobile phone bundled with your existing NBN provider
  • You may be getting some other bundle add-ons from your existing NBN provide
  • Another thing to consider is your use of a “landline” phone number. The packages offered by TPG offer a new phone number, and differing levels of included calls, from pay-as-you-go to included. If you want to retain the landline number you may currently use, then the number can be “ported” across to TPG in lieu of getting a fresh number.  To port the number to TPG, you will need to speak to their Sales Dept on 13 14 23

If you only use a mobile phone, then the free included phone line with the TPG-FTTB packages may be ignored.

DISCOUNT COUPONS

There is also a secret TPG Coupon you may be able to use that will waive your first month charge.

The coupon to try  is  FTTBFREE1   note: coupon may have expired

If you are an iiNet NBN customer, then you can sign up with them. They have a promo code at present of  ULTRA6 for 6 months @ $79.99. This may be only for new iiNet customers – not sure…

for TPG Sign Up:   TPG Link   or Phone  1300 403 211

for iiNet sign up:  online – iiNet Link  or Phone  13 19 17

TPG Package Details Below (iiNet are Similar)

Basic Bundle

New Pricing applies to new connections from December 2022

This bundle costs just $59.99 per month $79.99 for the first 6 months, then 89.99 per month  and would suit internet usage for emails and web browsing.

With a download speed of 90 Mbps, it would be way faster than any of your prior ADSL2 or NBN connection.

Upload speed is 17 Mbps,

Is very suitable for video streaming.

Includes a phone line with Pay As You Go.  Call rates are good, but most people today use Mobile Phones.

see TPG for further details

 

Local Development

4-8 Sutton Street

We have learned that an eight storey apartment building is to go ahead at 4-8 Sutton Street.  Works are scheduled to commence soon.

From the plans, it looks like it will be an attractive building.

One negative comment is that it will use rubbish chutes from each level for rubbish disposal.

There will be some two bedroom, some three bedroom and 2 four bedroom units. 26 Units in all. Most will only have one parking bay.

 

If you wish, click the Download Plans button here. It is a large file of over 10 Mbytes.

First New Paint Completion

Higgins Coatings are expected to complete the major painting works today, Aug 20 2019.

There may be a couple of painters around in the next few days to complete some minor issues.

Once all those issues are attended to we will update this article.

It has been a major effort by all present Committee and we have had a great deal of good advice and support from the Project Manager, Mr George Englert.

Keep A Lookout at Night

Dim The Lights

Dining on our balcony tonight, we were looking to the North, and at about 6:50pm, with low balcony lighting, there was a great display by either a meteorite or some space-junk.

There was a bright greenish object falling behind some scattered clouds. It was great to watch, even though it lasted only about 2 seconds.

So, always dim the lights and watch the skies.  And you don’t need to face North. This could have happened in any direction at any darker time.

Sorry, I do not have a photo of the event 🙁

 

First New Paint

Higgins Coatings commenced work yesterday on the repainting of the Waves Building.

Today, May 14th 2019, the first new paint was applied and this was on the balcony ceiling on an upper level apartment.

Please take note of the painting schedules as posted around the building and in particular, look out for any notice that may be placed under your front door. These notices from Higgins will arrive about 48 hours before work commences in and around your balcony. Please read them carefully.

 

New Roof Membrane Completed

Owners will be happy to know that the application of a new roof membrane has been completed, and just in time for Easter, 2019.

The process involved removal of failing membrane by using a diamond grinding machine and taking the roof back to the base concrete.

Next, a primer coat was applied, then the new membrane coat, followed by two ultra-violet protecting top coats.

The coating products were all supplied by Adcrete, a local industry, and the preparation and application was done by Vertex Access Systems.

Now, with care and re-inspection, the new membrane should last at least twenty years.

Roof Membrane – with Updates

Update: Thursday 14th March

The grind-off of the top (east) level roof has been completed today.
The two-pack primer coat has been applied to that area and will protect in case of rain.
It does look as though rain is coming later today so it is reassuring to know that the first sealing coat has been completed where needed.
Vertex plan to commence the grinding of the lower (Western) roof tomorrow, weather permitting.

Grinding the Roof - 11th March

Work by contractor "Vertex" has started today on the roof membrane replacement. You may hear some grinding noise within the building as the grinding progresses.

 

 

Grinding The Membrane

On the right is the grinder. In the left of the photo is the vacuum system to collect dust and debris from the diamond grinder.

 

 

Grinding The Membrane

This photo shows the inert material that is being removed. It is quite "rubbery" and flexible.
It is a shame that it was not applied uniformly when initially applied as the material seems in good condition where it is thick enough.

In many places it had been applied too thinly, and was worn through to the roof concrete. hence the need to have it all re-done.

Yes, there is some of this material blowing off the roof onto the grounds below. Vertex have been advised of this issue and are doing their utmost to minimize the problem. They are also cleaning affected areas each day as work progresses.  No "dust" gets past their HEPA filter system, only some larger fragments that are ejected from the grinding machine by centrifugal forces.

The material reaching the lower levels is inert, so just looks bad.

 

 

 

Old Membrane

Day Two

This photo shows two intrepid workers at the edge of the upper roof. Don't worry, they have tethers hooked onto their belts/harnesses.

And they are certified to work in such situations.

They are tethered to secure anchor bolts that have been re-certified within the past two days.

It is amazing the regulations that must be adhered to for such works.

Thanks to Carol (U27) for the photo...

 

 

 

 

Rooftop Workers

NBN at WAVES

New Fibre Optic

Today, 13-Feb-2019, I found a technician joining a new fibre optic cable at a pit at the south end of Sutton Street. I spoke to him briefly and he says it is a backbone fibre and will run all the way up Sutton Street.

Whilst we have HFC NBN at Waves, it may one day enable us to get the faster FTTB (Fibre to the Building) NBN and gigabit speeds.

Fibre on Sutton

September 2018 - Now Available

I checked today (29-Sept-2018) and I see that the NBN Co has recommenced new NBN connections for us here at Waves.

For first time NBN connections, be advised that the present cabling for your unit is only to the stage of a coiled up Coax lead that has been poked through the firewall above your Unit front door. It is accessible from the first light fitting, just inside your unit.

Any NBN installer will need to know that information about the cable in the previous paragraph. You will also need to decide where you want your NBN wall outlet. This is where your modem and phone (if any) will be located once installed, so plan carefully. It will also need to be near a power outlet.

The installers will extend the cable to where you want it, though in some cases you may have to be firm and demanding as to the location you want.

Choosing an NBN Retailer for Internet Service

When connecting to the NBN, you need to do so through an NBN retailer.

There are many of these, and they are not all the same. The biggest is Telstra, so if you are planning to go with Telstra, or your existing ADSL provider, then that would be the simplest route.

If you are searching around for a new provider, then be aware that most of them you will find are simply re-sellers.

One exception to this is a smaller Telco company, AussieBroadband.    AussieBB provide a great service with value for money. They also use only Australian Based help centres, so if you have an issue, it is more easily dealt with.

 

Choosing a VOIP Telephone Provider

When moving to the NBN, if you want a landline phone, you will be moving to a VoIP ( Voice over Internet Protocol) service. Your existing telephone line will disappear.

All existing phone landlines in Redcliffe will be disconnected at the end of June, 2019.

If you are planning to move from your existing phone line supplier, then consider using MyNetFone for your VoIP line. If you are keeping your NBN with your existing telco, then simplest is to keep your phone line with them.

But if you are moving from one provider to another for your NBN, then it is a good idea use separate providers for your NBN internet, and for your VoIP service. That way you can move one or the other between providers at any stage in the future.

Want to keep your existing phone number? Then the number can be "ported" across to your VoIP provider. Mostly this is with no charge, but sometimes may cost you a few dollars.

Any existing physical phone handset will work with VoIP, so no need for new phones.

 

AussieBroadBand


If you choose AussieBroadBand, (my chosen supplier and I can recommend them) then you can get the first month FREE by signing up online at aussiebroadband

For the free month it’s important that during the online signup process you enter the promo code WPFREEMONTH in the final stage of the check out process. This goes in the promo code field. With AussieBroadBand, there is no long term contract. They are not re-sellers but have their own direct connections to the NBN network. Their excellent phone support is all based in Australia.

Good luck. John, Unit 15

August 2018 Update

The NBN Co has announced that they will re-commence new HFC NBN connections in the Redcliffe area commencing late September 2018. Once we are able to confirm the availability of new connections we will post a message here.

A few units have had NBN now for several months, and it is very reliable and you are able to subscribe at higher speeds than those available with the legacy ADSL.

 

 

April 10th Update Announcement

Today (10-April-2018) the NBN Co announced that they would re-commence new HFC NBN connections in the Brisbane area commencing late June. It is not known yet if this will include the Redcliffe area, but it looks likely.

I have had NBN now for several months, and subscribed to the fastest available speed package of 100/40. There has only been two short outages that I have noticed since November. Each outage was less than 10 minutes.

(John Griffiths, Unit 15)

 

NBN to Suspend New HFC Connections

You may have read a press release from Monday Nov 27th where NBN have announced they are to suspend all new HFC nbn connections until they investigate and fix some reported network issues. Here is one report... Computerworld Article 

The announcement said that the suspension comes into effect immediately.
But there is still time if you wish to get onto the NBN network sooner than about 6-9 months from now.

Providers have been told that orders lodged by December 11th will be connected, but no new orders can be lodged after that date.
Some providers are still taking orders. So try contacting your chosen NBN provider ASAP and see if they will take your order now. If they won't, then I suggest you try AussieBroadBand as I know they are continuing to take orders until the deadline December 11th.

A Garden Guest

Today I spotted a large guest in the garden bed on the South side of the front entrances.

I think it is a skink, and it was about a foot long. Perhaps be wary when placing hands in the garden bed. I guess they bite!

JohnG

NBN Update September 2017

Update Monday 25-Sept. Several NBN suppliers now confirm that the service is available. These include Telstra, Optus, TPG, AussieBroadBand.


 Update Friday 22-Sept. There are a couple of owners who have been advised by different NBN suppliers that an NBN connection is now available at The Waves. A check of the NBN website does not yet confirm that, but that may just be because they have not yet updated their web site. More details will be posted here as more concrete information becomes available.

 


 

On Friday September 15 2017 there was a public meeting, organised by the local Federal representative, Luke Howarth, held at the Redcliffe RSL.

Several “Waves” residents were present and the meeting was filled to capacity.

There were presentations from representatives for the NBN, for Telstra, and for Optus.

Very little new information was presented, but the question time did provide some hope that we will get good quality internet service from our NBN connection when it becomes available.

At the end of the meeting, there was a chance to ask location specific questions of the NBN representatives. This I did and after queuing for about 10 minutes I had a chance to enquire as to the present status of the NBN connection here at Waves. here is what I was told;

  1. Some apartment buildings in our area have been changed from the HFC (Hybrid Fibre Cable) connection to the FTTB (Fibre To The Building). I was told that 17 Marine Parade is NOT one of those switched to FTTB.
  2. We will continue to be served using HFC. The connection is not yet available, but could be soon. No specific date is available yet, but Owners will be contacted by service providers once it is made available by NBN.
  3. The reason we have not yet been connected is for technical reasons and they (the NBN) has been working to overcome reported problems of current HFC users. To this end, the NBN are adding more coaxial cable runs in our area so as to reduce the number of households connected to any one cable section.
  4. Once our building connection is further tested and it meets necessary speed/capacity specifications we will be “switched on”.
  5. The connection to each unit will be via the coaxial cable NBN have already installed and which is in the ceiling just inside the front door of each unit, near the first light fitting.  See update note below .
  6. The HFC connection we will soon get, will be upgraded sometime by the end of 2018 to a much faster technology (DOCSIS3.1). Discover more about DOCSIS here

Regarding item 5 above:- (My opinion here) If you sign up NBN and have not pre-arranged to have a registered cabler install the necessary small wall-plate and coax terminus in your unit where YOU want it installed, then it is likely that when an NBN installer calls to do the install, the wall-plate will be installed near the power point closest to your front door. That lead-in is likely to be run down your wall in a conduit and be visible and unsightly.

If you want the new outlet close to where you have your current Modem/Phone/Computer, then you should organise the cabling before requesting an NBN service. Yes, it will cost you $$$s, but you will be assured of a connection where you want it and as neat and tidy as possible.

 Update Tues 3rd October.

Unit 15 has had the cabling completed, ready for the NBN technician to attach the necessary HFC modem. We plan for that to happen late November, as we will be away until about then.  The layout plan for our unit made it possible for our cable to be routed through the ceiling space to the laundry, Then it runs down the laundry wall in a neat channel, and then through the wall to a wallplate in our study area. Time taken by the cabler was 4 hours. Getting access to the laundry ceiling space was a fluke, as the wall panels seem to go all the way up to the concrete above.  There was one small opening we finally found where a previous electrician had created a hole.

John Griffiths, U15

NBN Update

Update: Aug 22, 2017.. A recent set of tests of a connection using a replaced splitter box in the Electrical Room in Ground Floor Garage was done about six weeks ago. It may still have shown speed problems and so we still need to wait for NBN co to write to us when all is ready. Yesterday NBN co announced that they would be conducting testing in four locations around Australia next February using the latest HFC (Hybrid Fibre Cable) connections using the DOCsis 3.1 transmission. Maybe we will be one of those locations??? If so, then we will be assured of very fast broadband speeds.



There has been recent NBN activity along Marine Pde, heading this way from around Mon Komo.

It looks as if they are getting ready to bring the fibre optic cable along the street and maybe soon we will have an NBN connection to the building.  The present indication is that we will get to use the Coaxial cable installed last year that was left coiled up in the ceiling in front of each apartment entrance.

More details will be sent direct to each unit owner in due course by the NBNco.
All the apartment blocks along Marine Pde are awaiting the new connection.

JohnG

The Way We Were

These old photos show what was at the Waves site before construction commenced.
Use the phone box as a reference.

Thanks to John Dunn for sending in those photographs.

Lending Library

Alison Dunn reports that-

 

Waves now has it’s own lending library for books, magazines and DVD’s.

Many thanks Alison (U23)

See below for details.

Got some items you would like to share? Add them to the collection.